More handi-work from the artisans.
The heavy-lifting construction is finally done. The carpenters worked till 8pm tonight to install the white zinc doors for the laundry area. They did a great job with the wooden powder room wall. No, it's not wall paper! It is made with 2" wide wood strips stained in 3 tones. Bet you can't find the door.
The solid tops for the kitchen and vanity were installed this morning. We made the right decision to use Dupont's Corian solid surfaces. The finishing looks great and it's eco-friendly.
The plumber installed the bathroom basin and mixer, shower mixer and accessories, and kitchen sink and mixer today. Unfortunately, the rainshower pipe doesn't fit and the powder room basin hasn't arrived. The plumber has to come back next week to complete the job.
Next week we will start on soft furnishing and touch-ups.